Telecom Order CRTC 2017-293
Ottawa, 21 August 2017
Various companies – Interim approval of tariff applications
- The Commission approves on an interim basis the following tariff applications:
Applicant Tariff Notice and description Date of application Effective date Shaw Cablesystems G.P. TN 30
General Tariff –
Introduction of Third-Party Internet Access Service 25 Mbps download and 2.5 Mbps upload speeds1 August 2017 21 August 2017 TELUS Communications Company TN 525
Carrier Access Tariff –
Withdrawal of Standby Circuits service4 August 2017 3 October 2017 TELUS Communications Company TN 526
Carrier Access Tariff –
Withdrawal of Test Facilities service4 August 2017 3 October 2017 - Revised tariff pages are to be issued within 10 calendar days of the date of this order. Revised tariff pages can be submitted to the Commission without a description page or a request for approval; a tariff application is not required.
Secretary General
- Date modified: