Telecom Order CRTC 2021-198
Ottawa, 9 June 2021
Northwestel Inc. – Interim approval of a tariff application
- The Commission approves on an interim basis the following tariff application:
Applicant Tariff Notice and description Date of application Effective date Northwestel Inc. TN 1124
Special Services Tariff – Introduction of Fibre Construction Service25 May 2021 9 June 2021 - The interim approval of this application complies with the 2006 and 2019 Policy DirectionsFootnote 1 by facilitating efficient tariff processes while enabling the Commission to consider, on the basis of a complete record, how its final decision can promote competition, affordability, consumer interests, and innovation.
- Revised tariff pages are to be issued within 10 calendar days of the date of this order. Revised tariff pages can be submitted to the Commission without a description page or a request for approval; a tariff application is not required.
Secretary General
- Date modified: