Telecom Decision CRTC 2021-106

PDF version

References: 2019-372, 2019-372-1, and 2019-372-2

Ottawa, 19 March 2021

Public record: 1011-NOC2019-0372

Broadband Fund – Project funding approval for Nexicom Inc.’s Ontario transport fibre project

The Commission approves Nexicom Inc.’s funding application for up to $1,251,719 to build transport infrastructure to serve five communities in Ontario.

Application

  1. In response to the Commission’s second call for applications for funding from the Broadband Fund set out in Telecom Notice of Consultation 2019-372, Nexicom Inc. (Nexicom) filed an application, dated 29 May 2020, in which it requested approximately $1.25 million from the Broadband Fund to implement a project that will provide a significant improvement in broadband service to five communities in Ontario.Footnote 1 Nexicom indicated that it will build approximately 25 kilometres of fibre optic transport network from Bewdley to Precious Corners, providing new points of presence (PoPs)Footnote 2 to the following communities: Camborne, Cold Springs, Gores Landing, Harwood, and Precious Corners.
  2. The project is expected to provide a capacity of 10 gigabits per second (Gbps) to each of the transport PoPs and connect up to six anchor institutions.Footnote 3 This project will improve resiliency and network diversity for communities in the surrounding area.

Commission’s analysis and determinations

  1. In Telecom Regulatory Policy 2018-377, the Commission established the eligibility and assessment criteria for the Broadband Fund. In Telecom Decision 2021-103, the introductory decision for the group of funding decisions issued today, the Commission provided background information and described the eligibility and assessment process and selection considerations used to assess and select projects to be funded. The introductory decision should be read in conjunction with this decision.

Eligibility criteria

  1. Nexicom’s application met each of the relevant eligibility criteria applicable to transport projects.Footnote 4 First, as a financially solvent and reliable Canadian carrier with more than three years’ experience deploying and operating broadband infrastructure in Canada, Nexicom met each of the criteria for eligible applicants. In addition, Nexicom demonstrated that it will invest more than a nominal amount in the project, and that the project would not be financially viable without funding from the Broadband Fund. Further, Nexicom provided evidence that it consulted with communities affected by the project, either directly or through community representatives. Finally, the project will serve eligible geographic areas and will meet the requirements regarding minimum capacity and wholesale and retail open access services. The Commission will continue to monitor the geographic eligibility of the project, using public or confidential information, to ensure that the geographic areas remain eligible for funding.

Assessment criteria

  1. On the basis of its evaluation of the project against the assessment criteria for transport projects,Footnote 5 as set out below, the Commission finds that Nexicom’s project is of high quality and will assist in achieving the goals of the Broadband Fund. 
  2. The project is technically sound, and the capacity proposed for the transport PoPs will facilitate providing broadband Internet access service to the above-mentioned region at the level of the universal service objective, which the Commission defined in Telecom Regulatory Policy 2016-496.Footnote 6 The proposed equipment is capable of delivering the proposed services, and additional capacity could be enabled in the future, making the project scalable. The project will implement widely adopted and supported technologies with good long-term sustainability. The network design includes the use of hardware that is resistant to damage and power backups to ensure that the network is resilient.
  3. Nexicom committed to providing wholesale and retail open access to the transport infrastructure. Nexicom submitted wholesale open access plans proposing dedicated service at various speeds and prices.
  4. The construction of transport infrastructure represents a long-term investment; a fibre transport network usually has an estimated useful life of 20 years or more. With this in mind, the Commission considered various financial indicators to assess the financial viability of the project and found it to be financially sound and the proposed costs to be reasonable.
  5. Nexicom provided evidence of support for the project from the mayor of the Township of Hamilton, which encompasses all five eligible communities affected by this application, and from Northumberland County, which is the municipal government for the Township of Hamilton.

Conclusion and directions

  1. In selecting the project for funding, the Commission considers that, due to the construction of the proposed transport PoPs, the project is consistent with the universal service objective, and concludes that the project will have a significant positive impact on the five communities to be served. In addition, the Commission concludes that supporting this project represents an efficient use of the funding available from the main component of the Broadband Fund.
  2. In light of all the above, the Commission approves, to the extent and subject to the terms and conditions set out below, up to a maximum of $1,251,719 from the Broadband Fund to be distributed to Nexicom for the purpose of the transport project described above and as set out in the approved statement of work. This approval is subject to the conditions that Nexicom
    1. confirm in writing, within 10 days of the date of this decision, its intent to submit a statement of work package to the Commission and to proceed with the project; and
    2. file for Commission approval, within 120 days of the date of this decision, a completed statement of work package in the format provided by the Commission, which includes an accompanying workbook that sets out the project budget, key project dates and schedules, and detailed project information, such as logical network diagrams, network descriptions, service designs, project sites, equipment details, maps, specific costs, and milestones.
  3. As established in Telecom Regulatory Policy 2018-377, project construction must not have begun prior to the date of this decision and should be completed within three years. As set out in the Application Guide, Nexicom may not apply for reimbursement of its costs until its statement of work has been approved by the Commission. Any eligible costs incurred prior to Commission approval of Nexicom’s statement of work but following the issuance of this decision are at Nexicom’s risk and will not be reimbursed if the statement of work is not approved.
  4. If it receives any additional funding for the project from any source, Nexicom must notify the Commission in writing as soon as possible and no later than 10 days after receiving the funding. The Commission may proportionately reduce the amount of funding it has approved.
  5. In order to receive funding, Nexicom must obtain Commission approval for (i) any material changes to the project, as set out in the approved statement of work; and (ii) any changes to Nexicom that would materially affect the legal or financial documents it provided during the application process. In order for the Central Fund Administrator to be able to distribute funding, Nexicom must sign the National Contribution Fund Administration Agreement if it has not already done so.
  6. The Commission will hold back 10% of the claimed amounts of funding until after construction of the network is complete. Holdback funds will be released only once the Commission is satisfied that Nexicom has been operating the network for one year according to the conditions of service set out below (see paragraphs 18 to 20).

Funding conditions

  1. In Telecom Regulatory Policy 2018-377, the Commission determined that it would impose a series of conditions (i) that must be met before it will release funding, and (ii) that ensure that the service to be provided using the funded infrastructure meets the promised service levels. The Commission indicated that funding conditions would be set based on project timelines, reporting, auditing, and material changes. Conditions imposed under section 24 of the Telecommunications Act (the Act) would be used to set the requirements for the ongoing operation of the network, including the speeds and capacity of services to be provided, pricing, and any reporting or measurement requirements. In addition, all existing regulatory obligations will continue to apply to the provision of services using funded infrastructure.Footnote 7
  2. Following Commission approval of the statement of work, the Commission will direct the Central Fund Administrator to release funds to Nexicom, provided that the company is in compliance with the following conditions:
    1. Nexicom must file a progress report, in the format provided by the Commission, outlining the progress made in the implementation of the project and any variances in the project schedule included in the statement of work. This report is to be filed every three months beginning on the date established in the statement of work and continuing until the project completion report is submitted. 
    2. Nexicom must file with the Commission every three months a Broadband Fund claim form certified by its chief financial officer, or by an equivalent authorized official of Nexicom, along with supporting documentation demonstrating to the Commission’s satisfaction that all costs claimed were actually incurred and paid and are eligible costs related to the activities described in the statement of work. Each claim form must be accompanied by a progress report.
    3. With respect to eligible and ineligible costs, as described in Telecom Regulatory Policy 2018-377, Nexicom must
      1. include eligible costs in a claim form submitted within 120 days of the costs being incurred, unless the costs were incurred after the date of this decision but prior to the approval of the statement of work, in which case the costs must be claimed on the first claim form submitted after the approval of the statement of work;
      2. ensure that all goods and services are claimed for reimbursement at amounts not greater than fair market value after deducting all trade discounts and similar items. Only the fair market value of the goods and services acquired is eligible for reimbursement; and
      3. measure and claim all goods and services received from related parties, as defined under International Financial Reporting Standards, at cost, with no profits or markups from the supplier.
    4. Nexicom must not claim in excess of 25% of the approved amount for costs incurred after the date of this decision but prior to the approval of the statement of work.
    5. Nexicom must ensure that its travel costs, such as meal per diems, comply with the National Joint Council Travel Directive.
    6. Nexicom must publicize, including by publishing on its website, the wholesale open access service packages to be offered as a result of the project at least 90 days prior to the planned date on which wholesale open access service will be available as detailed in the statement of work. This shall include the proposed location of any PoPs, capacity available for open access, service plans, prices, and terms and conditions.
    7. Where a risk of adverse impact on an Aboriginal or treaty right becomes known following the approval of the statement of work and a duty to consult exists, Nexicom must advise the Commission within 20 days and submit a plan detailing the form and process for fulfilment of the duty. Release of any additional funding will be contingent on demonstration that any necessary consultations were held to the Crown’s satisfaction.
    8. Nexicom must notify the Commission in writing as soon as possible and within no more than five days of becoming insolvent.
    9. Nexicom must file its annual financial statements with the Commission upon request. The financial statements would accompany the next progress report filed after the annual financial statements are completed and approved.
    10. Nexicom must ensure compliance with the Government of Canada’s national security requirements to address any potential risks related to the overall integrity of network security.
    11. Nexicom must file for Commission approval a project completion report within 90 days of completion of the final milestone in the statement of work. In the report, Nexicom must confirm that project construction is complete and that broadband services are being offered. The date on which construction is complete and broadband services are being offered will be considered the project completion date. Nexicom must also demonstrate in the report that the project has met the requirements set out in all related decisions. The report is to be in a format to be specified by the Commission.
    12. Nexicom must file a project holdback report one year after the project completion date demonstrating to the Commission’s satisfaction that Nexicom has been operating the network for one year in accordance with the conditions of service established in this decision and described in the approved statement of work.

Section 24 conditions

  1. In Telecom Regulatory Policy 2018-377, the Commission determined that it would impose, pursuant to section 24 of the Act, certain conditions regarding the offering and provision of broadband services using facilities funded through the Broadband Fund that would apply once the infrastructure is built. These conditions relate to the speeds and capacity of broadband services provided and the level of retail pricing, reporting, and associated open access service offerings. The conditions imposed on the offering and provision of broadband services will apply to Nexicom and to any other Canadian carrier operating the funded infrastructure.
  2. The Commission may conduct periodic audits and require measurements of the project’s performance to verify compliance with the conditions of funding and the conditions imposed pursuant to section 24 of the Act on the provision of services using the funded infrastructure. To that end, as a condition of offering and providing telecommunications services using the funded infrastructure, the Commission requires, pursuant to section 24 of the Act, that Nexicom, or any Canadian carrier operating the funded infrastructure, (i) retain all books, accounts, and records of the project, including administrative, financial, and claim processes and procedures, and any other information necessary to ensure compliance with the terms and conditions of this decision, for a period of eight years from the project start date; and (ii) provide the Commission with measurements of the performance of Nexicom’s implemented project within five years of the project’s completion date using methodology that the Commission may determine. The Commission may request that external auditors or a Commission-approved auditor certify any related report, form, or documentation, or that a third-party professional engineer certify any required measurements.
  3. In addition, pursuant to section 24 of the Act, as a condition of offering and providing telecommunications services using the funded infrastructure, Nexicom, or any Canadian carrier operating the funded infrastructure, must
    1. provide transport capacity at each eligible PoP funded by the Broadband Fund with total capacity no lower than that proposed in the application and described in the approved statement of work; and
    2. offer and provide, in a fair, transparent, timely, and non-discriminatory manner, wholesale and retail open access to the transport infrastructure at each eligible PoP funded by the Broadband Fund. Terms and conditions that are the same as or better than those applied to the services of subsidiaries, affiliates, or partners must be applied to other service providers requesting access to project sites. Such wholesale and retail open access services must be offered at rates no higher, and a capacity no lower, than those proposed in the application and detailed in the approved statement of work.

Policy Directions

  1. The 2006 Policy DirectionFootnote 8 and the 2019 Policy DirectionFootnote 9 (collectively, the Policy Directions) state that the Commission, in exercising its powers and performing its duties under the Act, shall implement the telecommunications policy objectives set out in section 7 of the Act, in accordance with the considerations set out therein,Footnote 10 and should specify how its decisions can, as applicable, promote competition, affordability, consumer interests, and innovation.
  2. The Commission considers that its decision to approve funding from the Broadband Fund for the project described in detail in this decision is consistent with the Policy Directions.
  3. Specifically, this decision to approve funding for a project to build transport infrastructure to serve five communities in Ontario will help to close the gap in connectivity in underserved areas. There would be no business case for the project without funding from the Broadband Fund. Funding the project will provide improved Internet services to the communities and thus respond to the social and economic needs of consumers. In doing so, this decision will implement the telecommunications policy objectives, including those set out in paragraphs 7(a), (b), and (h) of the Act.Footnote 11

Secretary General