Telecom Commission Letter Addressed to the Distribution List

Ottawa, 29 March 2018

Our reference:  8740-T66-201711250

BY EMAIL

Distribution

RE: TELUS Communications Inc. Tariff Notice 532 - Introduction of Service Entrance Conduit Charge – Extension Request for additional information

Dear Madam, Sir:

On 30 November 2017, the Commission received an application from TELUS Communications Inc. (TCI), Tariff Notice (TN) 532, in which the company proposed a revision to its General Tariff (CRTC 21461) Item 404, Support Structure Service, introducing a charge for service entrance conduit in British Columbia (B.C).

On 13 March 2018, Commission staff sent request for information related to the proposed TN 532, requesting the company’s response by 3 April 2018.

On 26 March 2018, the Commission received a submission from TCI stating that the supporting cost study associated TN 532 needs to be updated, and hence requesting a two week extension to provide responses.

Commission staff considers that TCI request is reasonable and therefore has revised the dates for this interrogatory process as follows:

Where a document is to be filed or served by a specific date, the document must be actually received, not merely sent, by that date.  Copies of the documents should also be sent to Abderrahman.elfatihi@crtc.gc.ca

Sincerely,

Original signed by

Lyne Renaud
Director, Competitor Services & Costing Implementation
Telecommunication sector
c.c.: El Fatihi, Abderrahman, Abderrahman.elfatihi@crtc.gc.ca

Distribution list:

TELUS Communications Company, regulatory.affairs@telus.com
Tom Woo, TELUS Communications Company, tom.woo@telus.com
Paul Cowling, Shaw Cable systems G.P., regulatory@sjrb.ca

Date modified: