Information identified as archived on the Web is for reference, research or recordkeeping purposes. Archived Decisions, Notices and Orders (DNOs) remain in effect except to the extent they are amended or reversed by the Commission, a court, or the government. The text of archived information has not been altered or updated after the date of archiving. Changes to DNOs are published as “dashes” to the original DNO number. Web pages that are archived on the Web are not subject to the Government of Canada Web Standards. As per the Communications Policy of the Government of Canada, you can request alternate formats by contacting us.
Ottawa, 6 February 2009
File No.: 8690-T66-200814774
Email distribution
Dear Sir/Madam:
Re: TCC’s application seeking an order to direct the ILECs to file new costs, terms and conditions for support structure service: request for cost information
On 30 October 2008, the Commission received an application from TELUS Communications Company (TCC), requesting that: (1) incumbent local exchange carriers (ILECs) be directed to file updated support structure cost studies in order to establish revised support structure service rates, terms and conditions, and (2) current ILEC support structure service rates be made interim with final rates to be adjusted retroactively.
It is noted that Bell Aliant Regional Communications, Limited Partnership (Bell Aliant), Bell Canada, MTS Allstream Inc. (MTS Allstream) and Télébec, Limited Partnership (Télébec) agree with TCC that the current support structure rates should be reviewed, that cost studies be filed and that, except for MTS Allstream, the rates be made interim. It is further noted that the cable carriers that participated in this proceeding opposed the review of rates for support structures submitting that the current support structure rates are capped, that TCC’s application amounts to a request to review and vary Revised regulatory framework for wholesale services and definition of essential service, Telecom Decision CRTC 2008-17, 3 March 2008, and that the application fails to demonstrate that there is substantial doubt as to the correctness of that Decision.
In order to assist the Commission to make determinations on the various issues raised in the proceeding initiated by TCC’s Part VII application, including the issues raised by the cable carriers, TCC, Bell Aliant, Bell Canada, MTS Allstream and Télébec are each requested to provide support structure cost studies, as well as, responses to the attached interrogatories, serving a copy on all other parties, by 1 April 2009. The above material must be actually received by the above date.
Yours sincerely,
Original signed by
Yvan Davidson
Senior Manager
Competitor Services and Costing
cc : Daphne Fry 819-953-5373
Attachment
Attachment
For Bell Aliant Regional Communications, Limited Partnership, Bell Canada, MTS Allstream Inc., and TELUS Communications Company
1. a) For each of the poles, strand (per 30 metres, or equivalent) and conduit (per 30 metres, or equivalent) support structure services, provide the prospective incremental cost and the associated embedded cost, expressed on a per unit basis.
b) Provide the methodology used in calculating the per unit embedded costs provided in a) above.
c) For each of the poles, strand (per 30 metres, or equivalent) and conduit (per 30 metres, or equivalent) support structure services, provide a comparison of the incremental and embedded per unit costs provided in response to part a) above with those provided in the proceeding leading to Access to Telephone Company Support Structures, Telecom Decision CRTC 95-13, 22 June 1995.
For Télébec
1. a) For each of the poles, strand (per 30 metres, or equivalent) and conduit (per 30 metres, or equivalent) support structure services, provide the prospective incremental cost and the associated embedded cost, expressed on a per unit basis.
b) Provide the methodology used in calculating the per unit embedded costs provided in a) above.
Distribution List
regulatory@bell.aliant.ca; bell.regulatory@bell.ca; michel.messier@cogeco.com ; iworkstation@mtsallstream.com; david.watt@rci.rogers.com; Regulatory@sjrb.ca; regulatory.affairs@telus.com; regaffairs@quebecor.com; regmat@ntl.sympatico.ca; natalie.macdonald@corp.eastlink.ca; legers@ca.inter.net; document.control@sasktel.sk.ca; lisangus@angustel.ca; y.brunelle@telephonelabaie.qc.ca; kirsten.embree@fmc-law.com; crtc@mhgoldberg.com; cataylor@cyberus.ca; ghariton@sympatico.ca; regulatory@flexity.ca; regulatory@execulink.com; progers@osler.com; regulatory@primustel.ca; canreg.affairs@alcatel-lucent.com; lefebvre@rogers.com; jhpratt@msn.com; dma2@telusplanet.net; cedwards@ccsa.cable.ca; agottlieb@gottliebgroup.ca; regulatoryca@aol.com; dennis.mudryk@gov.ab.ca ; regulatory@distributel.ca; john.lacalamita@ca.mci.com; antecol@phmlaw.com ; andre.labrie@mcccf.gouv.qc.ca; stinsond@comnet.ca; yb@comwave.net ; blackwell@giganomics.ca; abriggs@cogeco.ca; benrovet@rogers.com; tracy.cant@ontera.ca; RCI.Regulatory@rci.rogers.com; regulatory@lya.com; icollins@torontohydro.com; ldunbar@fasken.com; rob.olenick@tbaytel.com ; reglementation@xittel.net ; rancourt@consommateur.qc.ca; simon@globalive.com; thompson@oneconnect.ca; marcel.mercia@cybersurf.com; joe.parent@vonage.com; pruby@goodmans.ca ; jboutros@globility.ca ; piac@piac.ca; lynneanderson@hydroottawa.com; documents@accesscomm.ca; btithecott@atrianetworks.com; pdooling@enersource.com ; guatto@haltonhillsfibre.com; thare@blink.ca; tom@scbn.ca; icollins@torontohydro.com; corpoh@cfib.ca; Brady.Patricia@cb-bc.gc.ca; dean@personainc.ca; paul.marchant@hydroone.com; cpearson@epcor.ca; tom.copeland@eagle.ca; TomMoss@TelecomOttawa.com; tsullivan@wightman.ca ; jmcmaster@fibrewired.com ; jsebastien@cmaisonneuve.qc.ca; bagordon@rogers.com; regulatory@atrianetworks.com; pgale@mtotelecom.com; ctacit@tacitlaw.com
reglementation@xittel.net; reglementa@telebec.com