ARCHIVED - Telecom Order CRTC 99-1231
This page has been archived on the Web
Information identified as archived on the Web is for reference, research or recordkeeping purposes. Archived Decisions, Notices and Orders (DNOs) remain in effect except to the extent they are amended or reversed by the Commission, a court, or the government. The text of archived information has not been altered or updated after the date of archiving. Changes to DNOs are published as “dashes” to the original DNO number. Web pages that are archived on the Web are not subject to the Government of Canada Web Standards. As per the Communications Policy of the Government of Canada, you can request alternate formats by contacting us.
Telecom Order CRTC 99-1231 |
|
Ottawa, 23 December 1999 |
|
On 10 May 1999, TELUS Communications Inc. (TCI) filed an application for approval of an interconnection agreement between TCI and Northwestel Inc. (Northwestel). |
|
File No.: 8340-T42-0241/00 |
|
1. The Commission notes that the proposed agreement would replace the Telecommunications Interconnection and Service Agreement between TCI and Northwestel, dated 1 January 1996, as amended. |
|
2. The Commission notes that, as compared to the current agreement, the proposed agreement would have a negative effect on Northwestel's revenue. |
|
3. The Commission notes that it has initiated a proceeding (Northwestel proceeding), Northwestel Inc. – Implementation of toll competition and review of regulatory framework, quality of service and related matters, Telecom Public Notice CRTC 99-21, dated 1 October 1999. Among other things, it will assess the level of contribution required for Northwestel to achieve the basic service objective, address the terms and conditions that may permit long distance competition in Northwestel's operating territory, and determine whether any supplementary funding is required. The Commission is of the view that it would be appropriate for TCI and Northwestel to base their settlement payments on the current interconnection agreement until these issues are addressed. |
|
4. In light of the above, the Commission denies the application and directs TCI and Northwestel to continue to base their settlement payments on the current interconnection agreement dated 1 January 1996, as amended, until the decision in the Northwestel proceeding becomes effective. |
|
Secretary General |
|
This document is available in alternative format upon request and may also be viewed at the following Internet site: www.crtc.gc.ca |
- Date modified: