Information identified as archived on the Web is for reference, research or recordkeeping purposes. Archived Decisions, Notices and Orders (DNOs) remain in effect except to the extent they are amended or reversed by the Commission, a court, or the government. The text of archived information has not been altered or updated after the date of archiving. Changes to DNOs are published as “dashes” to the original DNO number. Web pages that are archived on the Web are not subject to the Government of Canada Web Standards. As per the Communications Policy of the Government of Canada, you can request alternate formats by contacting us.
Decision |
Ottawa, 11 September 1996
|
Decision CRTC 96-625
|
Heritage Cable Systems Inc.
|
Elgin, Delta, Spencerville and Morewood, Ontario - 199607537 - 199607545 - 199607553 - 199607561
|
Extension of construction deadline
|
Following Public Notice CRTC 1996-96 dated 5 July 1996, the Commission approves the application by Heritage Cable Systems Inc. to extend to 31 December 1996, the construction and implementation deadline for the undertakings authorized to serve Elgin, Delta and Spencerville; and for the extension of the cable distribution undertaking serving Morewood to include Marionville.
|
The Commission puts the licensee on notice that, should it be unable to complete construction and implement the above-noted undertakings and the extension to the Morewood undertaking by 31 December 1996, the Commission may not be prepared to grant a further extension and might reassess how these communities are to be served.
|
This decision is to be appended to each licence.
|