Broadcasting Decision CRTC 2018-363

PDF version

Reference: Part 1 application posted on 16 May 2018

Ottawa, 17 September 2018

Mass-Média Capitale inc.
Québec, Quebec

Public record for this application: 2018-0303-1

CJNG-FM Québec – Technical changes

  1. The Commission approves the application by Mass-Média Capitale inc. to change the authorized contours of the English-language tourist radio programming undertaking CJNG-FM Québec by relocating the antenna, decreasing the average effective radiated power (ERP) from 419 to 87 watts and the maximum ERP from 1,000 to 200 watts and decreasing the effective height of the antenna above average terrain from 132.9 to 110.8 metres. The Commission did not receive any interventions regarding this application.
  2. The licensee stated that it must relocate CJNG-FM’s antenna because the land and building on which it is installed have recently been sold and are no longer available.
  3. Pursuant to section 22(1) of the Broadcasting Act, this authority will only be effective when the Department of Industry notifies the Commission that its technical requirements have been met and that a broadcasting certificate will be issued.
  4. The transmitter must be in operation by 17 September 2020. To request an extension, the licensee must submit a written request to the Commission at least 60 days before that date, using the form available on the Commission’s website.

Secretary General

This decision is to be appended to the licence.

Date modified: